Note :-
# We can assist in RED marked work.
# Client can work for YELLOW marked works without our consultancy.
# WHITE marked works must complete with our company staffs.
- Preparation of drawings
- Marking
- Excavation
- Plain cement concrete floor slab with 40mm metal (1:4:8)
- Fixing of Pool drain box and necessary plumbing
- Steel reinforcement
- Mat concrete with 20mm metal & super plasticizer (1: 1.5 :3)
- Wall shuttering
- Wall concrete with 20mm metal & super plasticizer (1: 1.5 :3)
- Supply of skimmer or providing Balancing tank drawing
- Swimming pool leak checking
- Curing and leak test
- Pressure grouting from outside wall if you saw any leakage
- Application of polymer modified cementitious watertight coating
- Plastering with super plasticizer
- Providing Pump room drawing
- Pump room construct
- Connecting plumbing between plant room and pool
- Back filling around pool in 1feet layers and perfect consolidation
- Pump room electrical supply
- Waste water drainage arrangement from pump room
- Fixing of ladders
- Fixing of hand rails
- Coping stone laying on the top of pool wall
- Pool Tile laying with TILES ADHESIVES and SKILLED LABORS
- Inlet , Drain cover, vacuum fittings & Under water light fixing
- Installation of filter with filter sand , Pump, Starter.
- Swimming pool cleaning and water filling
- Trial run
- 3 days pool Maintenance training